Commercial Renovation Costs in Vancouver: Budget, Timeline and Process
Commercial renovation cost in Vancouver ranges from about $75 per square foot for a light refresh to $500 or more for a full-service restaurant. The type of space matters most. An office or shop mostly needs walls, finishes and lighting. A restaurant or cafe needs plumbing, ventilation and health approvals, and those systems are expensive.
This guide is the starting point for business owners planning any commercial project in Metro Vancouver. It covers cost per square foot by space type, what changes a budget, timelines, permits and the process from first site visit to handover. For a quote on your own space, our commercial renovation services start with a free site visit and a detailed estimate.
Key takeaways
- Typical 2026 Vancouver ranges: light refresh $75 to $120 per sq ft, mid-range fit-out $120 to $200, restaurant and medical-type spaces $200 to $300 or more.
- Mechanical, plumbing and electrical changes move a budget more than finishes do.
- Plan a contingency of 10 to 15% and budget soft costs separately.
- Commercial tenant improvements typically take 6 to 16 weeks of construction, plus design and permits.
- Under the 2025 Vancouver Building By-law, renovations under $255,000 no longer trigger structural or non-structural upgrades.
- A pre-lease assessment shows what a space really needs before you sign.
Commercial Renovation Cost per Square Foot by Space Type
The table below summarizes typical ranges for the spaces we build most often. Use it to sanity check a budget, not to replace a site visit. Two spaces of the same size and type can differ widely in cost depending on what is already there.
| Space type | Typical cost per sq ft | Main cost drivers |
|---|---|---|
| Light refresh (any commercial space) | $75 to $120 | Paint, flooring, lighting, minor millwork. No layout or mechanical changes. |
| Office | $80 to $220; Class A fit-up $165 to $295 | Walls and glass, ceilings, HVAC rebalancing, data cabling, AV. |
| Retail | $75 to $220 | Fixtures, lighting, storefront, flooring, change rooms. Standard fit-out $100 to $160; high-end $150 to $220. |
| Cafe or coffee shop | $100 to $450 | Bar and millwork, espresso utilities, plumbing, and whether a Type I hood is needed. |
| Restaurant | $150 to $500; fine dining $500 to $800+ | Kitchen, hood and fire suppression, grease interceptor, make-up air, washrooms. |
| Medical-type spaces | $200 to $300+ | Plumbing at many rooms, specialty electrical, ventilation, finishes that clean easily. |
| School or daycare | Varies widely | Pricing depends on licensing requirements, washrooms and fixtures sized for children, exits and safety features. |
Ranges are typical Vancouver market estimates for 2026, before GST, and are not a quote. Final numbers depend on the space. Suzuki Construction provides a free site visit and a detailed estimate.
For office projects, two independent guides are worth knowing. The Altus Group 2026 Canadian Cost Guide puts Vancouver Class A office interior fit-up at $165 to $295 per sq ft. The Cushman & Wakefield 2026 Office Fit-Out Cost Guide puts the average Vancouver hard cost at about $199 per sq ft, up from about $180.
What Changes a Commercial Renovation Budget
Finishes get most of the attention, but they rarely decide the budget. These factors usually do:
- Condition of the space. A second-generation space with working washrooms, adequate power and usable HVAC can save tens of thousands of dollars compared with an empty shell.
- Change of use. Turning retail into a restaurant, or an office into a daycare, brings new code requirements, more permits and often a development permit.
- Mechanical, electrical and plumbing work. On food service projects, these systems together often run about $50 to $100 per sq ft. Moving plumbing across a concrete slab is especially costly.
- Specialty systems. Commercial kitchen hoods, fire suppression and grease interceptors add large single line items.
- Accessibility. Washroom and entrance upgrades may be required when you alter a space.
- Building rules. After-hours work, elevator bookings, landlord-required trades and base building standards all add cost.
- Schedule pressure. Phased or overtime work to stay open costs more than working in an empty space.
Budget Categories: Hard Costs, Soft Costs and Contingency
A complete commercial renovation budget has four parts. Missing one is the most common reason owners run short of money.
Hard costs
Hard costs are the construction itself: demolition, framing, drywall, ceilings, flooring, millwork, mechanical, electrical, plumbing and specialty systems. Demolition alone typically runs $10 to $30 per sq ft. This is the number most people mean when they quote a cost per square foot.
Soft costs
Soft costs include design, engineering, permits, inspections, utility connection fees, insurance and legal fees. For a restaurant around 1,200 sq ft, permits and engineering alone often cost $8,000 to $18,000. Office and retail projects with fewer systems usually cost less to design and permit.
Furniture, fixtures and equipment
Desks, shelving, display fixtures, kitchen equipment, espresso machines, signage and IT hardware are often outside the construction contract. Budget for them separately and confirm who supplies and installs each item.
Contingency
Set aside 10 to 15% of the construction cost for surprises. Older buildings hide problems behind walls and under floors: outdated wiring, poor drainage or work that was never permitted. We issue written change orders before any extra work, so you approve every change before it happens.
Three Example Budgets
These are hypothetical examples to show how the numbers come together. They are not Suzuki projects.
Example 1: 1,500 sq ft retail store
Say a clothing brand leases a 1,500 sq ft unit on Main Street that was previously a gift shop. The layout works, but the brand needs new fixtures, lighting, a fitting room wall and a cash counter. At a standard retail fit-out rate of $100 to $160 per sq ft, the budget is about $150,000 to $240,000 before GST, plus contingency.
Example 2: 3,000 sq ft office
Say a consulting firm takes a 3,000 sq ft suite in Burnaby and wants a new layout with six private offices and two meeting rooms. At a mid-range fit-out rate of $120 to $200 per sq ft, the budget is about $360,000 to $600,000 before GST, plus contingency. Keeping the kitchenette near existing plumbing keeps the project toward the lower end.
Example 3: 1,200 sq ft casual restaurant
Say an owner converts a 1,200 sq ft former cafe in Richmond into a casual sit-down restaurant. At $200 to $350 per sq ft, the budget is about $240,000 to $420,000. A new hood, grease duct, make-up air and suppression system alone can cost $30,000 to $80,000 installed. If the previous tenant left a usable interceptor and washrooms, the total can drop noticeably.
How to Keep a Commercial Renovation on Budget
Most budget overruns start before construction. They come from a lease signed without checking the space, a scope that keeps growing during design, or drawings that miss what is behind the walls. A few habits prevent most of them.
- Assess the space before you sign. Find out whether the electrical service, plumbing, HVAC and drainage can support your business. Use what you learn to negotiate the rent, the rent-free period or a landlord contribution.
- Lock the scope early. Decide on layout, equipment and key finishes before permit drawings go in. Changes after permits are issued often need revisions and new reviews.
- Work with existing services. Keep sinks, washrooms and kitchens close to existing plumbing, and reuse ductwork where it works.
- Order long-lead items early. HVAC equipment, glass systems and specialty fixtures can take weeks to arrive.
- Insist on written change orders. Every change should be priced and approved in writing before the work happens.
- Compare estimates line by line. A low number that leaves out permits, demolition or mechanical work is not a lower price.
Above all, get a detailed estimate based on a site visit rather than a cost per square foot from a website, including this one. The ranges in this guide are a starting point for planning, not a substitute for looking at your actual space.
How Long Does a Commercial Renovation Take?
Construction time depends on the space type and scope. Our typical construction ranges are:
- Commercial tenant improvements in general: 6 to 16 weeks
- Office: 3 to 10 weeks
- Retail: 4 to 8 weeks
- Accessibility upgrades: 1 to 6 weeks
Planned well, even a busy retail location can be turned around quickly. For a Lonsdale Quay Market store in North Vancouver, the client noted that the whole construction lasted 45 days, as scheduled.
Construction is only one phase. A realistic schedule includes:
- Discovery and design: a few weeks for simple projects; about 4 to 6 weeks for restaurants.
- Permits: the City of Vancouver reported a median of 32 days for commercial renovation permits in 2024, down from 56 days in 2022. Low-complexity renovations can be approved in as little as 2 weeks, while complex projects or changes of use often take 8 to 16 weeks.
- Health approval for food businesses: about 2 to 8 weeks with Vancouver Coastal Health, often running at the same time as permits.
- Construction: 3 to 16 weeks depending on space type and scope.
- Inspections and handover: about 1 to 2 weeks for final inspections and occupancy.
Equipment lead times are a common cause of delay. HVAC equipment can take 6 to 12 weeks to arrive, so order it as soon as drawings are approved.
Our Commercial Renovation Process
Every project we build follows the same four stages. The goal is simple: no surprises on cost, schedule or quality.
- Discovery. We visit the site, listen to how your business works and review what the space has. For tenants still choosing a location, a pre-lease assessment checks electrical load capacity, plumbing rough-ins, HVAC capacity and drainage before you sign.
- Pre-construction. We coordinate design, engineering and permit drawings, including mechanical, plumbing, structural and fire-rated assemblies, and health authority requirements for food businesses. You receive a detailed estimate and schedule.
- Construction. One point of contact runs the job. You get daily progress updates with photos, progress payments tied to milestones and written change orders before any extra work.
- Post-project care and warranty. We complete commissioning, walk the space with you, resolve deficiencies and stay available after handover for warranty items.
Suzuki Construction is led by Rodrigo Suzuki, an architect and civil engineer with more than 20 years of experience, and Bruna Suzuki, who leads operations. You deal with the owners directly.
Permits for Commercial Renovations in Vancouver
The City of Vancouver requires permits for tenant improvements, changes of use, moving walls and relocating plumbing, electrical or gas. The City issues its own electrical, plumbing, gas and mechanical permits. A development permit is needed when zoning requires it, especially for a change of use, and you need an occupancy permit before you operate.
A few key points for business owners:
- The City’s commercial renovation checklist calls for drawings at a minimum 1/4 inch scale, architect Letters of Assurance for Part 3 buildings and engineers as systems change.
- Office tenants in listed buildings may use the Tenant Improvement Program, with an initial review in about 5 to 10 business days.
- Small businesses can get free help from the City’s Commercial Renovation Centre.
- Fire sprinkler permits are separate in Vancouver, and the City reports most go through a 24-hour fast track.
- Outside Vancouver, Technical Safety BC issues electrical and gas permits, except in cities that issue their own, such as Burnaby and the City and District of North Vancouver.
Food businesses need extra approvals, including Vancouver Coastal Health plan review and Metro Vancouver’s grease interceptor bylaw.
The 2025 Vancouver Building By-law and the $255,000 threshold
The 2025 Vancouver Building By-law took effect on September 15, 2025. Renovations under $255,000 no longer trigger structural or non-structural upgrades to the building. Tenant renovations with no effects outside the suite also face narrower upgrade requirements.
This matters for budgeting. A project just over the threshold may carry upgrade costs that a slightly smaller scope avoids. Ask your contractor and designer to check where your project sits early, before the scope is locked.
Accessibility Upgrades
Under BC Building Code 2024 section 3.8, accessibility requirements apply to alterations. Where washrooms are provided on an accessible storey, at least one must be a universal washroom. Vancouver removed its separate enhanced accessibility requirements in 2025 to match provincial rules.
In older buildings, this often means widening doors, adding ramps or rebuilding a washroom. Two accessible washrooms typically cost $25,000 to $50,000. Our accessibility renovation services cover universal washrooms, barrier-free entrances and related upgrades.
Commercial Spaces We Build
We have completed more than 300 projects across Metro Vancouver, from coffee bars to classrooms. Recent work shown on our site includes:
- Food service: Blenz Coffee, Veroni Espresso Bar, Jinya and Danbo. See our restaurant renovation services and coffee shop renovations.
- Office: Rewrite Capital Advisors. See our office renovation services.
- Commercial: Fairware and Car Club.
- Retail: a Lonsdale Quay Market store in North Vancouver. See our retail store renovations.
- Education: two PS School projects. See our school and educational facility renovations.
You can browse more in our commercial project portfolio.
Frequently Asked Questions
How much does a commercial renovation cost per square foot in Vancouver?
Typical 2026 ranges are $75 to $120 per sq ft for a light refresh, $120 to $200 for a mid-range fit-out, and $200 to $300 or more for restaurant and medical-type spaces. Full-service restaurants can exceed $500 per sq ft. These are estimates before GST, not a quote.
How long does a commercial renovation take?
Commercial tenant improvements typically take 6 to 16 weeks of construction. Offices often take 3 to 10 weeks and retail 4 to 8 weeks. Add time for design, permits and, for food businesses, health approval.
How much contingency should I budget?
Plan for 10 to 15% of construction cost. Older buildings and food service projects should lean toward the higher end, because hidden conditions are more common.
Do I need a permit for a commercial renovation in Vancouver?
Yes, for tenant improvements, changes of use, moving walls and relocating plumbing, electrical or gas. The City issues its own trade permits. A development permit may also be needed for a change of use.
What does the $255,000 threshold mean?
Under the 2025 Vancouver Building By-law, renovations under $255,000 no longer trigger structural or non-structural building upgrades. Projects above it may need to include upgrades, so check early.
Should I get a contractor to look at a space before signing a lease?
Yes. A pre-lease assessment checks electrical capacity, plumbing rough-ins, HVAC capacity and drainage. It tells you what the space will need and gives you facts to negotiate with the landlord.
Is it cheaper to take over a second-generation space?
Often. Existing washrooms, power, HVAC and, for food businesses, a hood or grease interceptor can save tens of thousands of dollars. Have them inspected first, because older systems may not meet current codes or bylaws.
Plan Your Commercial Renovation with Suzuki Construction
Suzuki Construction is an insured general contractor serving Vancouver, Richmond, Burnaby, Delta, North Vancouver, West Vancouver, Coquitlam, Port Moody and Surrey. We offer free consultations, detailed estimates and one point of contact from start to finish.
Learn more about our commercial renovation services in Metro Vancouver, or book your free site visit. You can also call us at (236) 515-7803.