Restaurant Build-Out Costs in Vancouver: What Business Owners Should Expect
A restaurant build-out starts long before construction. The space you choose, the lease you sign and what your landlord agrees to provide can swing your budget by tens or even hundreds of thousands of dollars. Many owners only discover this after the lease is signed, when it is too late to negotiate.
This guide is for business owners signing a new lease for a restaurant in Vancouver. It covers shell versus second-generation space, landlord work letters and tenant improvement allowances, what to check before you sign, the cost traps we see most often, and how to structure your budget. If you are already looking at spaces, our team handles restaurant renovation in Vancouver from pre-lease assessment through handover.
Key takeaways
- Your build-out budget is largely decided by the space and the lease, before any design work begins.
- Second-generation restaurant space can save tens of thousands of dollars if the existing systems work. A shell space means building everything from scratch.
- Know the difference between base building work (landlord) and tenant work (you), and negotiate it into the lease.
- A pre-lease assessment of electrical, plumbing, HVAC and drainage is the cheapest insurance a restaurant owner can buy.
- Kitchen equipment and furniture (FF&E) need their own budget, separate from construction.
- Plan for soft costs and a 10 to 15% contingency on top of hard construction costs.
What a restaurant build-out actually includes
A build-out is the construction work that turns a leased space into a working restaurant. In a new lease, that usually means more than a renovation: you may be installing systems that never existed, such as a kitchen exhaust hood, a grease interceptor or floor drains.
Typical Vancouver restaurant construction runs from about $150 per square foot for simple takeout concepts to $500 or more for full-service restaurants with a bar, according to 2026 market ranges. This article focuses on the decisions that come before those numbers.
Shell space vs second-generation restaurant space
The single biggest factor in a build-out budget is what is already in the space. There is no reliable published split in cost per square foot between shell and second-generation space, because it depends entirely on which systems exist and whether they work. But the difference is real and often large.
Shell space
A shell space is close to empty: a concrete floor, exterior walls, a roof and sometimes a basic electrical service stub. Everything a restaurant needs is built from scratch. That includes the kitchen hood and exhaust duct, make-up air, a grease interceptor, floor drains, washrooms, interior walls, ceilings and finishes.
Shell space gives you a clean slate for your layout. It also gives you the most work, the most permits and the longest schedule.
Second-generation space
A second-generation space was previously a restaurant. If the existing hood, grease interceptor, washrooms and electrical service are in good condition and suit your concept, reusing them can save tens of thousands of dollars.
The catch is the word “if.” A hood that is undersized for your cooking line, an interceptor too small for your fixture count, or washrooms that do not meet current accessibility rules still need replacing. Say you lease a 1,400 sq ft former sushi restaurant on Main Street and plan to open a burger concept with fryers and a flat-top grill. The sushi kitchen may have had light cooking with a small hood. Your menu may need a full Type I hood, a larger make-up air unit and more electrical capacity, so much of the “existing” kitchen gets replaced anyway.
Second-generation space is usually the better deal, but only after someone has checked what you are actually inheriting.
Landlord work letters and tenant improvement allowances
Commercial leases usually split the work between the landlord and the tenant. Understanding that split, and negotiating it, is one of the most effective ways to control your build-out cost.
Base building work vs tenant work
Base building work is what the landlord provides to make the space leasable. Tenant work is everything you need to make it your restaurant. The line between them is written in the lease, often in a schedule called a work letter. If it is not written down, assume it is your cost.
Items a landlord may provide as base building work include:
- Demising walls separating your unit from neighbours
- Base HVAC (a rooftop unit or heat pump sized for general use, not a kitchen)
- An electrical service to the unit, with a panel
- Washrooms, sometimes already built to accessible standards
- A water line and sanitary connection stubbed into the space
- Code-compliant fire sprinkler coverage for the base layout
Restaurant-specific items, such as the hood, grease duct, grease interceptor, make-up air and kitchen plumbing, are usually tenant work. Some landlords who want restaurant tenants will contribute to them. Many will not unless asked.
Tenant improvement allowance
A tenant improvement (TI) allowance is money the landlord contributes toward your build-out, often expressed per square foot or as a lump sum. It may be paid as a reimbursement after work is complete, or in stages. Read the conditions carefully: allowances often require invoices, lien releases and occupancy before any money is paid.
Our advice is simple: negotiate. Ask the landlord to cover base building items properly, ask for a TI allowance, and ask for a rent-free fixturing period long enough to cover permits and construction. Get the work letter reviewed by your lawyer and priced by a contractor before you sign. We do not provide legal or financial advice, but we can tell you what the work will cost, which gives you leverage in the conversation.
The pre-lease assessment: check before you sign
The cheapest time to find a problem is before the lease is signed. Suzuki Construction offers pre-lease assessments for restaurant owners. We visit the space and check the four systems that most often break restaurant budgets:
- Electrical load capacity. Can the existing service handle your cooking line, refrigeration, dishwasher and HVAC? Or will you need a service upgrade?
- Plumbing rough-ins. Where are the water, sanitary and vent lines? Can your sinks and floor drains connect without major slab cutting?
- HVAC capacity. Is the existing system adequate, and is there a practical way to add make-up air for a kitchen hood?
- Drainage. Is there a location for a grease interceptor, and is the sanitary line deep enough to serve it?
The result is a clear picture of what the space will need, which you can bring to the landlord and your lender before committing. Learn more on our restaurant renovation services page.
Hidden cost traps in a new restaurant lease
These are the issues that most often turn an affordable lease into an expensive build-out. Each one is worth checking before you sign.
Insufficient electrical service
Retail and office units are often served by electrical capacity far below what a commercial kitchen needs. A service upgrade can involve the utility, new switchgear and long equipment lead times. It is one of the largest single items in many restaurant budgets.
No gas line
If you plan to cook with gas and the unit has no gas service, a new line from the meter has to be run, sized and permitted. In the City of Vancouver, the City issues gas permits. Elsewhere, Technical Safety BC or the local city may handle them.
No route for the exhaust duct to the roof
A Type I hood needs a grease duct that runs to the exterior, usually through the roof. In a multi-storey building with residential units above, that route may be long, complicated or simply not allowed. A full hood, grease duct, make-up air and suppression system already runs $30,000 to $80,000 installed in typical cases. A difficult duct route pushes that higher, and no route at all can make the space unusable for cooking.
No space for a grease interceptor
The Metro Vancouver Food Sector Grease Interceptor Bylaw No. 365 requires restaurants to have a properly sized interceptor that is cleaned at least every 90 days. It needs a location that is accessible for maintenance and connected to the right drains. A tight unit may have nowhere suitable to put one.
Slab trenching for floor drains
Commercial kitchens need floor drains and sinks in specific places. If the existing sanitary lines are not nearby, the concrete slab has to be cut, trenched and patched. This is slow, messy work, and in a building with a parkade or occupied space below it can be more complicated still.
Sprinkler modifications
New walls, a new kitchen and new ceilings usually mean relocating or adding sprinkler heads. In Vancouver, fire sprinkler permits are separate, though the City reports that about 90% go through a 24-hour fast track. The cost is manageable when planned, and frustrating when discovered late.
Change of use triggering a development permit
Converting a retail or office unit into a restaurant is a change of use. Depending on zoning, that may require a development permit in addition to the building permit, which adds time, drawings and fees. Contractors commonly plan 8 to 16 weeks for permits on complex tenant improvements or changes of use.
Rough budget breakdown by category
Every space is different, but it helps to know roughly where the money goes. The table below is a rough, typical guide for a full restaurant build-out, as a share of the total project budget excluding kitchen equipment and furniture. Your split will vary, especially between shell and second-generation spaces.
| Budget category | Rough share of total | What it includes |
|---|---|---|
| Mechanical, electrical, plumbing and kitchen systems | 35 to 45% | Hood, grease duct, make-up air, HVAC, electrical service and distribution, plumbing, grease interceptor, gas |
| Interior construction and front-of-house finishes | 20 to 30% | Walls, ceilings, flooring, lighting, millwork, counters, bar, feature walls |
| Washrooms and accessibility | 5 to 8% | Accessible washrooms, entrance and path of travel |
| Demolition and site preparation | 2 to 5% | Strip-out, disposal, slab cutting and patching |
| Soft costs | 10 to 15% | Design, engineering, permits, health approval, insurance |
| Contingency | 10 to 15% | Unknown conditions, code requirements, owner changes |
Rough guide only, based on typical 2026 Vancouver market patterns. Ranges overlap and will not add to exactly 100%. Before GST. Not a quote.
In a shell space, the systems category tends to sit at the high end. In a good second-generation space, it shrinks and finishes take a larger share.
Soft costs: the part of the budget owners forget
Soft costs are everything that is not physical construction. They are easy to underestimate because they do not show up on a contractor’s line items unless you ask.
- Design. Layout, interior design and construction drawings. The City of Vancouver’s commercial renovation checklist calls for drawings at a minimum of 1/4 inch scale.
- Engineering. Mechanical engineering for the hood and make-up air, plumbing design, electrical design and sometimes structural work for rooftop equipment. Larger buildings require architect Letters of Assurance.
- Permits. Building, electrical, plumbing, gas, mechanical and sprinkler permits, plus a development permit if zoning requires one. For a 1,200 sq ft restaurant, permits and engineering together typically run $8,000 to $18,000.
- Vancouver Coastal Health. VCH must review and approve floor plans before construction, then inspect before you open. You also need a permit to operate. Plan 2 to 8 weeks for review.
- Business licence. The City of Vancouver now processes most business licences in about 2 days, with a $77 application fee plus an annual fee.
- Insurance. Your landlord will usually require proof of tenant insurance during construction, and your contractor should carry general liability and WorkSafeBC coverage.
- Contingency. Budget 10 to 15% for the unknown. In older Vancouver buildings, you will likely use it.
Also note the 2025 Vancouver Building By-law: since September 15, 2025, renovations under $255,000 no longer trigger structural or non-structural upgrades, but most full restaurant build-outs will exceed that threshold. Ask your designer early what upgrades your project may trigger.
FF&E and kitchen equipment: a separate budget
Furniture, fixtures and equipment (FF&E) are usually not part of the construction contract. That includes ranges, fryers, ovens, refrigeration, dishwashers, small wares, point-of-sale systems, dining furniture and decor.
Construction does include what connects equipment to the building: gas, power, water and drain hookups, the hood, and the fire suppression system. Make sure your contractor and equipment supplier agree on who supplies, sets and connects each item. Gaps between those two scopes are a common source of surprise costs right before opening.
Equipment selection also affects construction. A heavier cooking line needs more electrical capacity, a bigger hood and more make-up air. Finalize your equipment list before mechanical design, not after.
Thinking about financing
We are a contractor, not a financial advisor, so we will not tell you how to finance your restaurant. A few practical points from the construction side may still help.
- Lenders and landlords respond better to a detailed, line-item estimate than a single number.
- A TI allowance paid on completion means you need to carry those costs during construction.
- Progress payments tied to construction milestones make cash flow easier to plan than open-ended billing.
- Keep your contingency in reserve. Spending it on upgrades in week two leaves nothing for the problem found in week eight.
Talk to your accountant, lender and lawyer about structure. Bring them a real estimate.
How we approach restaurant build-outs
Suzuki Construction is a boutique, insured general contractor led by Rodrigo Suzuki, an architect and civil engineer with more than 20 years of experience, and Bruna Suzuki, who leads operations. We have worked on food service spaces for brands like Jinya, Danbo, Blenz Coffee and Veroni Espresso Bar.
Our process follows four steps: site assessment and requirements review; planning and permit coordination (mechanical, plumbing, structural, fire-rated assemblies and health authority compliance); construction and installation; and final commissioning and handover. Along the way you get written change orders before any extra work, milestone-based payments and daily photo updates.
Frequently asked questions
What is the difference between a restaurant build-out and a renovation?
A build-out usually means fitting out a newly leased space for restaurant use, often installing systems that never existed, such as a hood or grease interceptor. A renovation typically updates an existing restaurant. The two overlap, and costs depend on what is already in the space.
Is second-generation restaurant space always cheaper to build out?
Not always. It is usually cheaper when the existing hood, grease interceptor, washrooms and electrical service suit your concept and meet current codes. If they are undersized or outdated, much of the work still has to be done.
What does a landlord typically provide in a restaurant lease?
It varies by lease. Landlords may provide demising walls, base HVAC, an electrical service, washrooms and plumbing stubs as base building work, and sometimes a tenant improvement allowance. Restaurant-specific systems are usually tenant work unless you negotiate otherwise.
What should I check before signing a restaurant lease?
Check electrical load capacity, plumbing rough-ins, HVAC capacity, drainage and a location for a grease interceptor. Also confirm a route for the exhaust duct to the roof, gas availability and whether the change of use needs a development permit.
Are kitchen equipment and furniture included in build-out costs?
Usually not. FF&E, including cooking equipment, refrigeration and dining furniture, is typically a separate budget. Construction covers the hood, suppression and hookups that connect equipment to the building.
How much should I set aside for soft costs?
As a rough guide, soft costs such as design, engineering, permits, health approval and insurance often make up 10 to 15% of the total, with a further 10 to 15% contingency on top for unknown conditions.
Book a pre-lease assessment
Before you sign, find out what the space will really need. Suzuki Construction offers free consultations and pre-lease assessments across Vancouver, Burnaby, Richmond, North Vancouver, Surrey and the rest of Metro Vancouver.
Contact us to book your assessment, call (236) 515-7803, or learn more about our restaurant renovation services in Metro Vancouver.